Highbridge Anchor Park Reconstruction Phase I

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    65% complete

This project will reconstruct the staircase and pathways, including pavement, drainage, lighting and planting, in Highbridge Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: December 2018

Construction

Start Date: December 2018
Projected Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $10,755,000
Funding Sources:
  • Mayoral
  • City Council

Location

Highbridge Park , Manhattan
West 181st Street to Dyckman Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/05/2020