Highbridge Anchor Park Reconstruction Phase I
-
100% complete
-
100% complete
-
87% complete
This project will reconstruct the staircase and pathways, including pavement, drainage, lighting and planting, in Highbridge Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: November 2016
Projected Completion Date:
December 2017
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
September 2018
Completion
Date:
December 2018
Construction
Start Date: December 2018
Projected Completion Date:
June 2020
Adjusted Completion
Date:
April 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Highbridge Park
, Manhattan
West 181st Street to Dyckman Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/15/2021