Astoria Park Charybdis Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Charybdis Playground in Astoria Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: September 2019

Construction

Start Date: February 2020
Projected Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $2,401,000
Funding Source: Mayoral

Location

Astoria Park , Queens
Between Shore Boulevard and 19th Street at 23rd Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/05/2020