Astoria Park Charybdis Playground Comfort Station Reconstruction
-
100% complete
-
100% complete
-
48% complete
This project will reconstruct the comfort station at Charybdis Playground in Astoria Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: May 2017
Projected Completion Date:
May 2018
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
September 2019
Construction
Start Date: February 2020
Projected Completion Date:
August 2021
Adjusted Completion
Date:
November 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Astoria Park
, Queens
Between Shore Boulevard and 19th Street at 23rd Road
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 01/15/2021