Astoria Park Charybdis Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    13% complete

This project will reconstruct the comfort station at Charybdis Playground in Astoria Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: September 2019

Construction

Start Date: February 2020
Projected Completion Date: August 2021
Adjusted Completion Date: November 2021

Understand how we build parks.

Funding

Total Funding: $2,400,000
Funding Source: Mayoral

Location

Astoria Park , Queens
Between Shore Boulevard and 19th Street at 23rd Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/26/2020