Astoria Park Charybdis Playground Comfort Station Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Charybdis Playground in Astoria Park.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Astoria Park , Queens
Located East of Shore Boulevard, Borough of Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 06/22/2018