Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground Comfort Station.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: December 2017
Projected Completion Date: November 2018
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Adjusted Completion Date: December 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 04/15/2021