Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    52% complete

This project will reconstruct Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground Comfort Station.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2017
Projected Completion Date: November 2018
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Completion Date: May 2021

Construction

Start Date: June 2021
Projected Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $1,697,000
Funding Sources:
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/05/2022