Forest Park Garage and Oak Ridge Roof Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct roofs at Forest Park Garage and Oak Ridge in Forest Park.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: December 2017
Projected Completion Date: July 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million

Location

Forest Park , Queens
Forest Park Garage and Oak Ridge in Forest Park, Queens.

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/19/2018