Forest Park Garage and Oak Ridge Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    54% complete

This project will reconstruct roofs at Forest Park Garage and Oak Ridge in Forest Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Completion Date: July 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $2,335,000
Funding Source: Mayoral

Location

Forest Park , Queens
Myrtle Avenue, Union Turnpike, Park Lane South

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 04/07/2020