Forest Park Garage and Oak Ridge Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct roofs at Forest Park Garage and Oak Ridge in Forest Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: December 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Completion Date: July 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $3,075,000
Funding Source: Mayoral

Location

Forest Park , Queens
Forest Park Drive between 76th Street and 79th Street

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 08/19/2019