West 48th Street & 10th Avenue (DEP Shaft Site 25B) New Park Construction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a new open space at West 48th Street and 10th Avenue.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: February 2019
Projected Completion Date: February 2020
Adjusted Completion Date: January 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

West 48th Street and 10th Avenue

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/19/2020