Beach 108th Street Esplanade Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Beach 108th Street Esplanade.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: March 2019
Projected Completion Date: September 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Federal

Location

Park at Beach 108 Street , Queens
Beach Channel Drive between Beach 108th Street and Rockaway Freeway

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/19/2020