Beach 24th and 25th Streets Ramps Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct ramps to the Rockaway Beach Boardwalk at Beach 24th Street and Beach 25th Street.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: October 2019
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Federal

Location

Rockaway Beach and Boardwalk , Queens
Rockaway Beach Boardwalk at Beach 24th Street and Beach 25th Street.

 