Shore Front Parkway Multi-Purpose Area Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct a multi-purpose sports field at Shore Front Parkway.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: October 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: August 2020
Adjusted Completion Date: March 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • Borough President
  • Federal

Location

Rockaway Beach Boardwalk , Queens
Shore Front Parkway between Beach 81st Street and Beach 77th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/19/2020