Shore Front Parkway Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    97% complete

This project will construct a dog run along Shore Front Parkway.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: July 2019
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: May 2020
Completion Date: August 2021

Construction

Start Date: September 2021
Projected Completion Date: September 2022

Understand how we build parks.

Funding

Total Funding: $1,838,000
Funding Sources:
  • Borough President
  • Federal
  • Mayoral

Location

Rockaway Beach Boardwalk , Queens
Shore Front Parkway at Beach 90th Street

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 07/01/2022