NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Shore Front Parkway Dog Run Construction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a dog run along Shorefront Parkway.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: July 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Federal

Location

Rockaway Beach Boardwalk , Queens
located between Beach 92nd and Beach 90th along Shorefront Parkway

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/21/2018

Was this information helpful?