Rockaway Community Park Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Rockaway Community Park.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: December 2018
Projected Completion Date: June 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Federal

Location

Rockaway Community Park , Queens
Almeda Avenue, Norton Avenue, Beach 58th Street, Sommerville Basin, Beach 49th Street, Conch Basin

 

Project Staff

Contact NYC Parks about this project

Last updated: 06/24/2019