Rockaway Community Park Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Rockaway Community Park.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: December 2018
Projected Completion Date: June 2020
Adjusted Completion Date: December 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Federal

Location

Rockaway Community Park , Queens
Almeda Avenue, Norton Avenue, Beach 58th Street, Sommerville Basin, Beach 49th Street, Conch Basin

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020