NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

FY19 Staten Island NRG Reforestation

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees to mitigate wildfire in Staten Island

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: March 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million

Location

Various locations, Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 02/16/2018

Was this information helpful?