Staten Island Reforestation FY19

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees to mitigate wildfires in Staten Island.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million

Location

Various locations in Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 11/16/2018