Staten Island Reforestation FY19

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    43% complete

This project will remove invasive species and plant new and replacement trees to mitigate wildfires in Staten Island.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: November 2018
Completion Date: June 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2024

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Various locations in Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020