Staten Island Reforestation FY19

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees to mitigate wildfires in Staten Island.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million

Location

Various locations in Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 08/17/2018