Bushwick Inlet Park (50 Kent Avenue) New Park Construction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a portion of Bushwick Inlet Park at 50 Kent Avenue.

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Start Date: June 2018
Projected Completion Date: July 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Bushwick Inlet Park , Brooklyn
Kent Avenue between North 11th Street and North 12th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/16/2019