Bushwick Inlet Park (50 Kent Avenue) New Park Construction
-
100% complete
-
100% complete
-
92% complete
This project will construct a portion of Bushwick Inlet Park at 50 Kent Avenue.
Project Update: This project is in active construction.
Project Timeline
Design
Start Date: June 2018
Projected Completion Date:
July 2019
Completion Date:
August 2019
Procurement
Start Date: August 2019
Projected Completion Date:
May 2020
Completion
Date:
March 2021
Construction
Start Date: April 2021
Projected Completion Date:
April 2022