Sheepshead Bay Piers Electrical & Structural Components Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the electrical and structural components at Sheepshead Bay Piers.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: September 2020

Procurement

Start Date: September 2020
Projected Completion Date: June 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Federal

Location

Sheepshead Bay Piers , Brooklyn
Emmons Avenue between East 21st Street and East 26th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/12/2021

Was this information helpful?