Franz Sigel Park Ballfields Reconstruction and Lighting & Scoreboard Construction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct two natural turf ballfields and construct sports lighting and a score board in Franz Sigel Park.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: October 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

Franz Sigel Park , Bronx
Walton Avenue, Grand Concourse, East 158th Street, East 151st Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 04/19/2019