Fox Playground Comfort Station Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct a comfort station in Fox Playground.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Fox Playground , Bronx
East 156th Street between Fox Street and Southern Boulevard

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/19/2019