Police Officer Edward Byrne Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct a comfort station in Police Officer Edward Byrne Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Borough President

Location

Police Officer Edward Byrne Park , Queens
North Conduit Avenue, 130th Place, 135th Avenue, 130th Place, 134th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 04/19/2019