Betsy Head Park Multi-Purpose Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    97% complete

This project will construct a new skate park, basketball courts, fitness area and multi-purpose space in the northern parcel of Betsy Head Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: January 2018
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Completion Date: December 2018

Construction

Start Date: December 2018
Projected Completion Date: December 2019
Adjusted Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $6,270,000
Funding Source: Mayoral

Location

Betsy Head Park , Brooklyn
Blake Avenue between Thomas S. Boyland Street and Bristol Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/05/2020