Betsy Head Park Multi-Purpose Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    65% complete

This project will construct a new skate park, basketball courts, fitness area and multi-purpose space in the northern parcel of Betsy Head Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: January 2018
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Completion Date: December 2018

Construction

Start Date: December 2018
Projected Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $6,270,000
Funding Source: Mayoral

Location

Betsy Head Park , Brooklyn
Blake Avenue between Thomas S. Boyland Street and Bristol Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/13/2019