Bartlett Playground Reconstruction
-
100% complete
-
100% complete
-
83% complete
This project will reconstruct Bartlett Playground.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
April 2020
Construction
Start Date: October 2020
Projected Completion Date:
April 2022
Adjusted Completion
Date:
May 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bartlett Playground
, Brooklyn
Bartlett Street and Whipple Street between Throop Avenue and Harrison Avenue
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 05/25/2022