Bartlett Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    83% complete

This project will reconstruct Bartlett Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: April 2020

Construction

Start Date: October 2020
Projected Completion Date: April 2022
Adjusted Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $8,051,000
Funding Source: Mayoral

Location

Bartlett Playground , Brooklyn
Bartlett Street and Whipple Street between Throop Avenue and Harrison Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/25/2022