Bartlett Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct Bartlett Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: April 2020

Construction

Start Date: October 2020
Projected Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $8,051,000
Funding Source: Mayoral

Location

Bartlett Playground , Brooklyn
Bartlett Street and Whipple Street between Throop Avenue and Harrison Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/28/2020