Bushwick Inlet Park Motiva Parcel Remediation and Passive Seating Area Construction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will remediate and construct a new passive seating area in Bushwick Inlet Park.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: January 2019
Projected Completion Date: July 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Bushwick Inlet Park , Brooklyn
Franklin Street, Kent Avenue, East River, Quay Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/22/2019