Bushwick Inlet Park Motiva Parcel Remediation and Passive Seating Area Construction
-
90% complete
-
0% complete
-
0% complete
This project will remediate contaminated soils and construct a new passive seating area in Bushwick Inlet Park.
Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.
Project Timeline
Design
Start Date: January 2019
Projected Completion Date:
July 2020
Adjusted Completion Date:
April 2022
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bushwick Inlet Park
, Brooklyn
Franklin Street, Kent Avenue, East River, Quay Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 08/15/2022