Kelly Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct and expand the playground in Kelly Park, including play equipment, spray shower, swings, seating areas, benches, security lighting, fencing, drainage and water supply, electrical service, and plantings.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: May 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million

Location

Kelly Park Playground , Brooklyn
Avenue S between East 14th Street and East 15th Street

 