Kelly Park Playground Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct and expand the playground in Kelly Park, including play equipment, spray shower, swings, seating areas, benches, security lighting, fencing, drainage and water supply, electrical service, and plantings.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: November 2019
Projected Completion Date: November 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: State

Location

Kelly Park Playground , Brooklyn
Avenue S between East 14th Street and East 15th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/19/2020