Kelly Park Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct and expand the playground in Kelly Park, including play equipment, spray shower, swings, seating areas, benches, security lighting, fencing, drainage and water supply, electrical service, and plantings.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
May 2021
Procurement
Start Date: May 2021
Projected Completion Date:
January 2022
Adjusted Completion
Date:
October 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Location
Kelly Park Playground
, Brooklyn
Avenue S between East 14th Street and East 15th Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 06/27/2022