Randall's Island Emergency Utility Transformer Systems Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This emergency project will reconstruct the utility transformer systems at Randall's Island.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: April 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: November 2018

Construction

Start Date: September 2018
Projected Completion Date: January 2019
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $650,000
Funding Source: Mayoral

Location

Randall's Island Park , Manhattan
Near Icahn Stadium

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/14/2019