Randall's Island Emergency Utility Transformer Systems Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This emergency project will reconstruct the utility transformer systems at Randall's Island.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: April 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Randall's Island Park , Manhattan
Near Icahn Stadium

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/15/2018