Starr Playground Play Area and Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the playground and spray shower at Starr Playground.

Project Update: Design is complete.

Project Timeline

Design

Start Date: September 2019
Projected Completion Date: September 2020
Completion Date: October 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Location

Starr Playground , Queens
Onderdonk Avenue between Starr Street and Willoughby Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/19/2020