Hallets Cove Seawall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    88% complete

This project will reconstruct damaged portions of the seawall and railing at Hallets Cove.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: April 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: April 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Adjusted Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $6,549,000
Funding Source: Mayoral

Location

Hallets Cove Playground , Queens
Along the East River from Hallets Cove Playground at Vernon Blvd to Hallets Point Playground at Astoria Blvd and 1st Street.

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 05/26/2022

Was this information helpful?