Hallets Cove Seawall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    81% complete

This project will reconstruct damaged portions of the seawall and railing at Hallets Cove.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: April 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: April 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $6,549,000
Funding Source: Mayoral

Location

Hallets Cove Playground , Queens
Along the East River from Hallets Cove Playground at Vernon Blvd to Hallets Point Playground at Astoria Blvd and 1st Street.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/23/2021

Was this information helpful?