Astoria Park Track and Field Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the track and field in Astoria Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Astoria Park , Queens
Bounded by Shore Blvd, RFK Bridge, 9th street and Astoria Park South.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 06/22/2018