Astoria Park Track and Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the track and field in Astoria Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Construction

Start Date: November 2018
Projected Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $11,295,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Astoria Park , Queens
Shore Boulevard, RFK Bridge, 18th Street, Astoria Park Sout.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/12/2018