St. Mary's Park Plaza, Pathways, and Gil Scott-Heron Amphitheater Reconstruction
-
100% complete
-
100% complete
-
83% complete
This project will reconstruct the plaza, pathways, lighting, and Gil Scott-Heron Amphitheater at St. Mary’s Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: July 2017
Projected Completion Date:
July 2018
Completion Date:
August 2018
Procurement
Start Date: August 2018
Projected Completion Date:
April 2019
Completion
Date:
July 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2021
Adjusted Completion
Date:
May 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
St. Mary's Park
, Bronx
St. Anns Avenue between East 143rd Street and East 149th Street
Project Staff
Project Liaison: Mike Ortiz
Contact NYC Parks
about this project
Last updated: 07/05/2022