St. Mary's Park Amphitheater, Plaza, and Pathways Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the amphitheater, plaza, pathways and lighting at St. Mary's Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

St. Mary's Park , Bronx
St. Anns Avenue between East 143rd Street and East 149th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/07/2018