St. Mary's Park Amphitheater, Plaza, and Pathways Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will reconstruct the amphitheater, plaza, pathways and lighting at St. Mary's Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: April 2019
Completion Date: July 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $19,688,000
Funding Source: Mayoral

Location

St. Mary's Park , Bronx
St. Anns Avenue between East 143rd Street and East 149th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/12/2019