St. Mary's Park Plaza, Pathways, and Gil Scott-Heron Amphitheater Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    83% complete

This project will reconstruct the plaza, pathways, lighting, and Gil Scott-Heron Amphitheater at St. Mary’s Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: April 2019
Completion Date: July 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2021
Adjusted Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $19,682,000
Funding Source: Mayoral

Location

St. Mary's Park , Bronx
St. Anns Avenue between East 143rd Street and East 149th Street

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 07/05/2022