Highland Park Pedestrian Paths and Sidewalks Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    3% complete

This project will reconstruct the sidewalk and improve pedestrian access along a portion of Highland Boulevard.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $1,036,000
Funding Source: Mayoral

Location

Highland Park , Queens
Highland Boulevard between Jamaica Avenue and Vermont Place

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/27/2020