Highland Park Pedestrian Paths and Sidewalks Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the sidewalk and improve pedestrian access along a portion of Highland Boulevard.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: November 2019

Construction

Start Date: August 2020
Projected Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $1,036,000
Funding Source: Mayoral

Location

Highland Park , Queens
Highland Boulevard between Jamaica Avenue and Vermont Place

 