Staten Island Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the basketball courts, paths, fencing, landscape and park amenities at Wolfe's Pond Park, Old Town Playground, and Midland Field.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 11/16/2018