Classic Playground Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct adult fitness equipment at Classic Playground in Van Cortlandt Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: November 2021

Procurement

Start Date: November 2021
Projected Completion Date: August 2022
Adjusted Completion Date: December 2022

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

Van Cortlandt Park , Bronx
Van Cortlandt Park South between Orloff Avenue and Hillman Avenue

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 09/23/2022

Was this information helpful?