Flushing Meadows Corona Park Adult Fitness Equipment Installation

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will install adult fitness equipment in Flushing Meadows Corona Park.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: April 2019
Adjusted Completion Date: November 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Flushing Meadows Corona Park , Queens
Corona Avenue and 111th Street, next to Playground for All Children

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/14/2019