Flushing Meadows Corona Park Adult Fitness Equipment Installation

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will install adult fitness equipment in Flushing Meadows Corona Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: April 2019
Adjusted Completion Date: September 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Flushing Meadows Corona Park , Queens
Corona Avenue and 111th Street, next to Playground for All Children

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project