Flushing Meadows Corona Park Adult Fitness Equipment Installation

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will install adult fitness equipment in Flushing Meadows Corona Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Flushing Meadows Corona Park , Queens
Corona Avenue and 111th Street, next to Playground for All Children

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 06/19/2019