Bowery & East 4th Street (DEP Site) New Open Space Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

The project will construct a new open space at the DEP site on East 4th Street between Bowery and Lafayette Street.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: July 2020
Completion Date: October 2021

Construction

Start Date: November 2021
Projected Completion Date: October 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,270,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Bowery & East 4th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/25/2022

Was this information helpful?