Commodore Barry Park Ballfields Reconstruction and Track and Sports Lighting Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the natural turf ballfields and construct new sports lighting and a track around the ballfields in Commodore Barry Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: April 2022

Procurement

Start Date: April 2022
Projected Completion Date: January 2023

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Commodore Barry Park , Brooklyn
Park Avenue between Navy Street and North Elliot Place

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/01/2022

Was this information helpful?