Bath Beach Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct and expand the playground, including new play equipment, new pavements, safety surfacing, site furnishings, drainage, and water supply; demolish the bocce courts and multipurpose play area and construct sitting and adult fitness areas; and reconstruct the central path in Bath Beach Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Procurement

Start Date: February 2020
Projected Completion Date: November 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

Bath Beach Park , Brooklyn
Shore Parkway between Bay 14th Street and Bay 16th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/19/2020