Penn Triangle Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    45% complete

This project will reconstruct Penn Triangle.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: October 2019

Construction

Start Date: November 2019
Projected Completion Date: November 2020
Adjusted Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $1,719,000
Funding Source: Mayoral

Location

Penn Triangle , Brooklyn
Penn Street, Wythe Avenue, Williamsburg Street East

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/22/2020