Madison Square Park Pavement Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the pavement in the southern portion of Madison Square Park.
Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.
Project Timeline
Design
Start Date: March 2019
Projected Completion Date:
March 2020
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Madison Square Park
, Manhattan
East 23rd Street, 5th Avenue, East 26th Street, Madison Avenue
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/15/2021