Riverside Park 102nd Street Staircase Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the staircase at West 102nd Street in Riverside Park.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: December 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Riverside Park , Manhattan
West 102nd Street and Riverside Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/11/2018