Sunset Park Handball Court Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the handball court in Sunset Park.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date:
June 2019
Procurement
Start Date: June 2019
Projected Completion Date:
March 2020
Adjusted Completion
Date:
November 2020
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Sunset Park
, Brooklyn
44th Street, 41st Street, Fifth Avenue, Seventh Avenue
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/15/2021