Babi Yar Triangle Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and seating area at Babi Yar Triangle.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,482,000
Funding Sources:
  • Mayoral
  • City Council

Location

Babi Yar Triangle Playground , Brooklyn
Brighton 14th Street, Oceanview Avenue, and Corbin Place

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/25/2022

Was this information helpful?