Asser Levy Park Adult Fitness Area Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct adult fitness equipment in Asser Levy Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021
Adjusted Completion Date: October 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Asser Levy Park , Brooklyn
Surf Avenue and West 5th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project