Booker T. Washington Playground Synthetic Turf Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the synthetic turf field, basketball backstops, and chain link fencing at Booker T. Washington Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: March 2019
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: December 2019

Construction

Start Date: April 2020
Projected Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $1,845,000
Funding Sources:
  • Mayoral
  • City Council

Location

Booker T. Washington Playground , Manhattan
West 107th Street, West 108th Street, Amsterdam Avenue, Columbus Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/27/2020