Harold Ickes Playground BMX Bike & Skate Park and Multipurpose Play Area Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct a BMX bike, skate park and multipurpose play area at Harold Ickes Playground.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Borough President
  • City Council

Location

Harold Ickes Playground , Brooklyn
Hamilton Avenue between Van Brunt Street and Woodhull Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2019