Mellett Playground Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the children's play area in Mellett Playground with new steel play equipment, spray shower, pavements, site furniture, security lighting, landscaping, and utilities.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020
Adjusted Completion Date: May 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Location

Mellett Playground , Brooklyn
Avenue V between East 13th Street and East 14th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/19/2020