Mellett Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    28% complete

This project will reconstruct the children's play area in Mellett Playground with new steel play equipment, spray shower, pavements, site furniture, security lighting, landscaping, and utilities.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: February 2020
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $2,295,000
Funding Sources:
  • Mayoral
  • City Council

Location

Mellett Playground , Brooklyn
Avenue V between East 13th Street and East 14th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/19/2021