Mellett Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    87% complete

This project will reconstruct the children's play area in Mellett Playground with new steel play equipment, spray shower, pavements, site furniture, security lighting, landscaping, and utilities.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: February 2020
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $2,295,000
Funding Sources:
  • Mayoral
  • City Council

Location

Mellett Playground , Brooklyn
Avenue V between East 13th Street and East 14th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/20/2022