Doughboy Plaza Seating Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the seating area surrounding the monument at Doughboy Plaza, including the drinking fountain and pathways.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $1,876,000
Funding Source: City Council

Location

Doughboy Park , Queens
Woodside Avenue between 54th Street and 56th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/16/2021

Was this information helpful?