Vanderbilt Motor Parkway Reconstruction Phase 1

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct a Vanderbilt Motor Parkway from Winchester Boulevard to Springfield Boulevard.

Project Update: The schematic design for this project has been approved. Parks is now developing construction documents for this project and applying for necessary permits.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Locations

  • Alley Pond Park , Queens
    Little Neck Bay to Springfield Boulevard, Union Turnpike
  • Motor Parkway , Queens
    Cloverdale-Hollis Court Boulevards, Kingsbury-Richland Avenues
 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/19/2018