Devoe Park Perimeter Steel Gates Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    86% complete

This project will install steel gates for the perimeter fence at Devoe Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: September 2017
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $105,000
Funding Source: Mayoral

Location

Devoe Park , Bronx
West Fordham Road, Sedgwick Avenue, Webb Avenue, Father Zeiser Place, University Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/15/2018