Devoe Park Perimeter Steel Gates Installation

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will install steel gates for the perimeter fence at Devoe Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: September 2017
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $500,000
Funding Source: Mayoral

Location

Devoe Park, Bronx
Devoe Park located between West Fordham Road, Sedgwick and Webb Avenues, Father Zeiser Place and University Avenue, Borough of the Bronx.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/16/2018