St. Mary's Park Playground West Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will reconstruct the comfort station at St. Mary's Park Playground West.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $3,119,000
Funding Sources:
  • Mayoral
  • City Council

Location

St. Mary's Park , Bronx
St. Ann's Avenue and East 147th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/02/2020