St. Mary's Park Playground West Comfort Station Reconstruction
-
100% complete
-
100% complete
-
24% complete
This project will reconstruct the comfort station at St. Mary's Park Playground West.
Project Update: This project is in active construction.
Project Timeline
Design
Start Date: May 2017
Projected Completion Date:
May 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
March 2019
Completion
Date:
November 2019
Construction
Start Date: September 2020
Projected Completion Date:
March 2022
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
St. Mary's Park
, Bronx
St. Ann's Avenue and East 147th Street
Project Staff
Project Liaison: Michelle Martell
Contact NYC Parks
about this project
Last updated: 04/13/2021