St. Mary's Park Playground West Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at St. Mary's Park Playground West.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $3,119,000
Funding Sources:
  • Mayoral
  • City Council

Location

St. Mary's Park , Bronx
St. Ann's Avenue and East 147th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 08/07/2020