Anne Loftus Playground Spray Shower Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the spray shower plaza, children's climber play equipment, and safety surfacing at Anne Loftus Playground in Fort Tryon Park.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date:
August 2019
Procurement
Start Date: August 2019
Projected Completion Date:
May 2020
Adjusted Completion
Date:
March 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Fort Tryon Park
, Manhattan
Broadway and Riverside Drive
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 02/25/2021