Anne Loftus Playground Spray Shower Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the spray shower plaza, children's climber play equipment, and safety surfacing at Anne Loftus Playground in Fort Tryon Park.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: June 2018
Projected Completion Date: June 2019
Adjusted Completion Date: August 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Fort Tryon Park , Manhattan
Broadway and Riverside Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/23/2019