Poor Richard's Playground Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the play area at Poor Richard's Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Poor Richard's Playground , Manhattan
3rd Avenue between East 108th and East 109th Streets

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/12/2020