Audubon Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    80% complete

This project will reconstruct Audubon Playground.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Construction

Start Date: October 2018
Projected Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $7,137,000
Funding Source: Mayoral

Location

Audubon Playground , Manhattan
Audubon Avenue between West 169th Street and West 170th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/01/2020