Audubon Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    80% complete

This project will reconstruct Audubon Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Construction

Start Date: October 2018
Projected Completion Date: April 2020
Adjusted Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $7,137,000
Funding Source: Mayoral

Location

Audubon Playground , Manhattan
Audubon Avenue between West 169th Street and West 170th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/07/2020