Audubon Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Audubon Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Construction

Start Date: October 2018
Projected Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $5,584,000
Funding Source: Mayoral

Location

Audubon Playground , Manhattan
Audubon Avenue between West 169th Street and West 170th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/16/2018