Prescott Playground Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

The playground is being reconstructed to improve fencing, repair existing walls, and replace aged play equipment, and pavements.

Project Update: The schematic design for this project has been approved. Parks is now developing construction documents for this project and applying for necessary permits.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

E.M.T. Christopher J. Prescott Playground , Staten Island
The playground is located on the corner of Irvington Street and Edith Avenue.

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 08/17/2018