Prescott Playground Reconstruction
-
100% complete
-
100% complete
-
54% complete
This project will reconstruct Prescott Playground, including fencing, retaining walls, play equipment, and pavements.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
November 2019
Construction
Start Date: January 2020
Projected Completion Date:
January 2021
Adjusted Completion
Date:
April 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
E.M.T. Christopher J. Prescott Playground
, Staten Island
Irvington Street and Edith Avenue
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 02/26/2021