Lopez Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    46% complete

This project will reconstruct Lopez Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: January 2019
Completion Date: January 2019

Procurement

Start Date: January 2019
Projected Completion Date: October 2019
Completion Date: December 2019

Construction

Start Date: March 2020
Projected Completion Date: May 2021
Adjusted Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $3,037,000
Funding Sources:
  • Mayoral
  • City Council

Location

Lopez Playground , Staten Island
Palma Drive between Targee Street and Oder Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/19/2020